Benefits of extended thermocouple installations on HRSG tubes

Contact Us
Table of Contents

If your plant suffers from frequent failures, installing additional thermocouples can prove to be invaluable when assessing the actual root cause of the failures.

During a recent Tetra project in the Middle East, a number of thermocouples were installed at the top and bottom headers joining economizer tubes which had previously been subject to failures.  The thermocouples were positioned around one of the failure locations to clearly map temperature distributions on the tubes, during various operational conditions.  Tetra built looms of K-type weldable cable that was routed inside the boiler and capacitance discharge welded to the tubes of interest.  Although the front rows of tubes were very easy to attach the thermocouples to it was felt that more information would be obtained by getting the group around the failed area. Thermocouples were welded to the tubes in the area where fins had already been welded but then removed as part of the tube manufacturing process. 

After the installation, the plant could easily log various operating conditions and send the data back to the Tetra office for analysis. 

For more information about thermocouple installation contact Dave Moelling dave.moelling@tetra-eng.com (Americas) or Mark Taylor mark.taylor@tetra-eng.com (EMEA).

Book a free consultation

Our goal is to protect the value of your investments and improve the performance of your assets.

Contact Us

More News

Stay up to date and refer to our large collection of technical white papers and articles

HRSG Tube Failure Guide, 3rd Ed.
News

HRSG Tube Failure Guide, 3rd Ed.

The latest updated edition of Tetra Engineering's HRSG Tube Failure Diagnostic Guide will be published August 15, 2016. Thousands of combined cycle professionals are familiar with Tetra's HRSG Tube Failure Diagnostic Guide; first published during the 'bubble' in construction in the early 2000s.

Learn more
Predicting and Preventing HP Evaporator Tube Failures
News

Predicting and Preventing HP Evaporator Tube Failures

Two of the most common issues that power plant owners and operators face in the HP Evaporator section areUnder-deposit Corrosion (UDC) andCorrosion-Fatigue. In this short article we will cover UDC and what key actions should be taken to predict and prevent costly forced outages.

Learn more
T23 Tube Failure
News

T23 Tube Failure

During the startup of the triple-pressure HRSGs, plant staff noticed steam coming from the stack and a discrepancy between feedwater and steam flows. On shutting down the unit a T23 superheater tube was found with a complete circumferential failure. The failed tube was removed and the bore was plugged with some difficulty due to poor access and the uncommon material.

Learn more

Contact Us

To discuss how we might assist you to improve your plant's performance or to maintain its value over time

Contact Us