
Impact of Startup Purge Credit on Combined Cycle Plant Operation
Normal boiler and Heat Recovery Steam Generator Operation have required a complete purge of the boiler by fresh air before startup firing to remove potentially explosive fuels and other substances from the boiler/HRSG. For power plants in daily two-shift cycling (or more frequent starts) this not only adds time to the startup sequence but can impose significant thermal stresses on hot components exposed to cooler purge air.