On-Site Services

Posted in Services

HRSG Combined Cycle Power Plant Boiler

From the front to the back of the boiler (or HRSG), the extreme conditions faced by pressure parts are a challenge for any designer to overcome. The same applies to other components in the steam cycle, from the condensers, to the Power Piping, and of course the steam turbine.

Degradation is an unfortunate but inevitable reality for the power plant’s pressure equipment. Effective operation and maintenance (O&M) of the plant requires informed management of maintenance activities during planned shutdowns and demands judicious responses to unexpected failures. It is difficult to achieve the delicate balance of having optimal thermal process performance, maintaining appropriate water/steam chemistry while controlling O&M costs that will minimize equipment wear and aging.

With over 25 years of experience in thermal power plants – including conventional plants with radiant boilers (gas, oil, coal, biomass), and combined cycle plants with HRSGs – at Tetra Engineering we have the required resources and competence to support you during planned (or unplanned) outages and to assist you remotely in preparation.

Our field services include:

  • HRSG or Boiler Visual Inspection: This basic activity is the best measure of the boiler’s present condition – don’t leave it to amateurs.
  • Hot Walkdowns: For in-service inspection of equipment including checking for leaks and performing thermography
  • Hot/Cold Piping Inspection: If you haven’t adjusted any piping supports for the last five years, your team is probably not inspecting them!
  • NDE Inspection Planning and On-site Supervision: Optimise outage resources by targeting NDT inspection locations – avoid the trap of letting NDE contractors decide where to inspect.
  • Welding Repair / Refurbishment Supervision: Unsupervised welding activities are a recipe for trouble. Experience shows that paper quality does not equal weld quality.
  • Online Tuning of Control Systems: Reduce the unnecessary cycling of equipment and improve the safety measures that protect your equipment.

About Us

Established in 1988, Tetra Engineering has more than 25 years experience providing solutions to the power industry. We specialize in solutions for HRSGs, conventional boilers & steam-cycle balance of plant.